2/27/00 - 3/8/00

3/3/00: Today I waited for the glass guys to install our shower door and sides. They were to show up between 1:00 and 3:00PM TODAY. The phone rang at 3:10, it was the glass guy whining about how bad traffic was and that he would not be able to make it. So let's see, do these guys make it on the companies that suck list? They quoted us a two week delivery on 2/5/00. On 3/2/00 (two weeks overdue)  they finally called to schedule our installation. On the day of our appointment, after the time they should have been here had passed, they call and tell me they can't make it. Ro is letting them have it on the phone right about now.

3/8/00: The bathroom is finished!

 

 

wpe17.jpg (25456 bytes)

The shower surround finally installed.